鄂北地区水资源配置工程建管信息系统研发

沈松勇1,李 喆1,季庆辉2,陈希炽1   

  1. 1. 空间信息技术应用研究所,武汉 430010;
    2.鄂北地区水资源配置工程建设与管理局筹,武汉 430071
  • 收稿日期:2016-07-20 出版日期:2016-11-20 发布日期:2016-11-08
  • 作者简介:沈松勇(1984-),男,湖北武汉人,工程师,硕士,主要从事水利测绘、水利信息化等工作,(电话)027-82926469(电子信箱)milton840626@126.com。
  • 基金资助:

    湖北省水利厅信息化重点项目(CKSF2016023/KJ);中央级公益性科研院所基本科研业务费项目(CKSF2015019/KJ)

Design and Implementation of Construction Management InformationSystem for North Hubei Water Transfer Project

SHEN Song-yong1, LI Zhe1, JI Qing-hui2,CHEN Xi-chi1   

  1. 1.Spatial Information Technology Application Department, Yangtze River Scientific Research Institute, Wuhan430010, China;2.Construction and Management Bureau of Water Resources Allocation Project inNorthern Hubei Province (Planning), Wuhan 430071, China
  • Received:2016-07-20 Online:2016-11-20 Published:2016-11-08

摘要:

针对鄂北地区水资源配置工程项目投资大、工期紧、输水线路长、工程建设环节复杂、参建单位多,人员素质参差不齐,容易产生规范化施工水平不足的问题,根据水利部颁发的水利工程建设管理相关技术规范及《鄂北地区水资源配置工程基建统计管理办法》等内部管理文件,采用Microsoft C#+Microsoft SQL Server 2012数据库方式,研发了鄂北地区水资源配置工程建管信息系统。该系统已经在丹襄建管部、枣随建管部、广悟建管部进行了3个月的试运行。结果表明,系统增加了多类型用户复杂权限管理能力,规范了信息填报审核工作流程,提高了基建统计工作效率,更形象地展示了工程建设过程场景,实现了水利工程建设过程管理的规范化、透明化、痕迹化、流程化,大大提升了鄂北地区水资源配置工程信息化水平。

关键词: 水资源配置, 建管信息系统, 鄂北地区, 基建统计填报, 三维可视化

Abstract:

The North Hubei Water Transfer Project is the biggest water resource project in Hubei Province. It has problems inclusive of big investment,limited construction period,long water conveyance line,complex engineering process,many construction units involved,and uneven personnel quality.In view of this,according to technical specifications for hydro-project construction management issued by the Ministry of water resources and several internal management documents issued by the Administration of the North Hubei Water Transfer Project such as Infrastructure construction management measures for the North Hubei Water Transfer Project, we designed and implemented the information system for the construction management of North Hubei Water Transfer Project with the combination of Microsoft C# and Microsoft SQL Server 2012 program languages. The system has already been used for trial in Danjiangkou-Xiangyang construction management branch, Zaoyang-Suizhou branch, and Guangshui-Dawu branch for three months. Results show that with the aid of the system, the complex hierarchical management of multi-type users is improved, the information reporting process is standardized, the efficiency of infrastructure statistics construction is enhanced, and the engineering construction process scenario is better displayed. The work flow is standardized, transparent, and can be traced, which suggests that the information level of the North Hubei Water Transfer Project is improved remarkably.

Key words: water resources allocation, construction management information system, North Hubei Province, statistical reporting and summary of infrastructure construction, 3D visualization