院报 ›› 2015, Vol. 32 ›› Issue (3): 15-19.DOI: 10.3969/j.issn.1001-5485.2015.03.004

• 区域水土保持 • 上一篇    下一篇

输油管道工程特征及其水土流失防治措施——以平原区和丘陵区为例

陈兰1,周鸿基2,刘纪根1,王一峰1,牛俊1   

  1. 1. 水土保持研究所,武汉 430010;
    2.长江水利委员会 水土保持局,武汉 430010
  • 收稿日期:2015-01-16 出版日期:2015-03-01 发布日期:2015-03-06
  • 作者简介:陈 兰(1988-),女,湖北天门人,助理工程师,硕士,研究方向为水土保持规划与设计,(电话)027-82926205(电子信箱)chenlan1002@126.com。
  • 基金资助:

    国家自然科学基金项目(41001166,41101260); 创新团队资助项目(CKSF2012052/TB)

Engineering Characteristics of Oil Pipeline and Control Measures for Soil and Water Loss: Case Study on Plain Area and Hilly Area

CHEN Lan1,ZHOU Hong-ji2,LIU Ji-gen1,WANG Yi-feng1,NIU Jun1   

  1. 1.Soil and Water Conservation Department,Yangtze River Scientific Research Institute, Wuhan 430010,China;
    2.Bureau of Water and Soil Conservation, Changjiang Water Resources Commission, Wuhan 430010, China
  • Received:2015-01-16 Online:2015-03-01 Published:2015-03-06

摘要:

为了在输油管道建设过程中采取合理的水土流失防治措施,减少水土流失,对输油管道工程的项目组成、施工组织进行了分析,重点介绍了一般管道敷设和穿越公路、铁路、河流段管道敷设施工工艺。在平原区和丘陵区作为一级分区的基础上,将输油管道工程分为管道作业带区、穿越工程区、站场阀室区、施工便道区和施工生产区5个防治分区。对分段管道的防治目标值加权平均得到工程的水土流失防治目标值,在此基础上分别确立了平原区和丘陵区输油管道工程的水土流失防治措施体系,分析工程措施、植物措施和临时措施的特点,因地制宜地采取合理措施来减少输油管道工程建设过程中的水土流失。研究成果为输油管道工程的水土流失防治措施提供了参考依据。

关键词: 输油管道工程, 水土流失, 施工组织, 施工工艺, 防治措施

Abstract:

The aim of this research is to reduce soil and water loss by taking appropriate countermeasures during the construction of oil pipeline projects. The composition, construction organization and techniques of oil pipeline construction are analyzed. The techniques of laying ordinary pipeline and pipelines crossing highway, railway, river are introduced in emphasis. Moreover, pipelines in plain area and hilly area are partitioned and are further divided into 5 sub-zones (pipe laying zone, crossing zone, station and valve chamber zone, construction road zone, and construction zone). The objectives of soil and water loss are determined by the weighting of objectives of each segment. On this basis, systems of different countermeasures for hilly area and plain area are established, and the features of engineering measures, plant measures, as well as temporary measures are analyzed. Appropriate measures are adjusted according to specific local conditions. This research is a reference for the control of soil and water loss for oil pipeline project.

Key words: oil pipeline project, soil and water loss, construction organization, construction technology, prevention and control measures

中图分类号: 

Baidu
map