高堆石坝施工挡水风险的时变性和填筑进度的不确定性增加了坝体施工期度汛方案决策的难度。针对高堆石坝施工度汛过程动态变化的特点,随机模拟大坝挡水风险,并将其划分3个风险状态以判断度汛行动。以整个度汛施工期成本最小化为目标,考虑洪水来流、填筑进度和决策成本等关键因素,建立基于马尔科夫过程的高堆石坝施工度汛决策模型,分析逐月大坝挡水风险状态下的度汛策略、成本函数和风险状态转移概率。在检验其马尔科夫特性基础上,采用决策迭代算法求解每一决策时刻状态下的最优施工度汛方案及度汛过程的决策路径。工程实例分析表明,该决策模型对高堆石坝施工度汛计划策略的调控结果符合实际施工度汛高程变化情况,为指导快速准确制定大坝施工度汛方案提供了参考。
Abstract
Time variation of water-retaining risk and uncertainty of filling progress aggravate the difficulties in making decision for high rock-fill dam construction in flood period. Accordingly, the water retaining risk of high rock-fill dam was calculated by stochastic simulation, and then was classified into three risk states which could indicate the decision actions. With the objective of minimizing the cost of the entire construction process in flood season, the critical factors such as incoming flood flow, filling schedule and cost of decisions were taken into account to build a decision-making model based on Markov Processes. By using this model, the flood prevention strategies, cost functions and transfer probability for each risk degree were analyzed. After testing the Markov property, the optimal strategy for each state at current time and a sequential risk decision path in this process can be predicted by strategy iteration method. A study case shows that the adjustment results by the proposed model consists well with the actual construction plan change for water retaining elevation. The results offer reference for timely and accurate flood prevention scheme in construction period.
关键词
高堆石坝 /
施工度汛 /
风险决策 /
马尔科夫过程 /
成本最小化
Key words
high rock-fill dam /
construction in flood period /
risk decision making /
Markov Process /
cost minimizing
{{custom_sec.title}}
{{custom_sec.title}}
{{custom_sec.content}}
参考文献
[1] 刘 潋,胡志根.时变条件下高堆石坝施工度汛协商决策的演化分析模型[J].水利学报,2013,44(11):1359-1365.
[2] 范锡峨,胡志根,刘 全.基于效用的施工导流方案多目标决策模型[J].中国工程科学,2008, 10(7):137-140.
[3] RASEKH A, AFSHAR A, AFSHAR M. Risk-cost Optimization of Hydraulic Structures: Methodology and Case Study[J].Water Resources Management, 2010, 24(11): 2833-2851.
[4] 钟登华,毛寨汉,刘东海.施工导流方案的多目标总体综合评价方法[J].水利水电技术,2002,33(5): 17-20.
[5] 张 超,胡志根.高堆石坝中期度汛挡水风险率估计[J].水科学进展,2014,25(6):873-879.
[6] 李宗坤,葛 巍,王 娟,等.改进的突变评价法在土石坝施工期风险评价中的应用[J].水利学报, 2014,45(10):1256-1260.
[7] 刘 潋,胡志根.高堆石坝施工度汛挡水风险动态控制模型研究[J].水力发电学报,2015,35(2):82-89.
[8] 薛进平,胡志根,刘 全.施工导流方案动态交互协商决策[J].系统工程理论与实践,2014,34(11):2995-3000.
[9] 刘 克,曹 平.马尔可夫决策过程理论与应用[M].北京:科学出版社,2015.
[10]胡志根,刘 全, 贺昌海.等.基于Monte-Carlo方法的土石围堰挡水导流风险分析[J].水科学进展,2002,13(5):634-638.
[11]崔金铁.坝体施工期临时度汛问题探讨[J].水利规划与设计,2006,(2):44-46.
[12]HANSEN E A, ZILBERSTEIN S. LAO*: A Heuristic Search Algorithm that Finds Solutions with Loops[J]. Artificial Intelligence, 2001, 129 (1/2): 35-62.
[13]MOON T, WEISSMAN T. Universal Filtering via Hidden Markov Modeling[J]. IEEE Transactions on Information Theory, 2008, 54(2): 692-708.
[14]张玉芬,朱雅琳.马尔可夫性及其检验方法研究[J].价值工程,2012,31(2): 312-313.
基金
国家自然科学基金项目(51509143);raybet体育在线
开放研究基金项目(CKWV2016398/KY)